ARIDA 3 SOLAR FARM
BetaActiveSolarBatteryCAISOLBNL + Live
900 MW hybrid in Clark, NV · In queue since April 2020 · Proposed COD July 2030
900 MW
Capacity
2
Components
Solar + Battery
5y 11m
In Queue
System Impact Study
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
10y 3m
Impact Study25%
Queue EntryApr 15, 2020
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-07-01
Technology
Solar450 MW · 50%
Battery450 MW · 50%
Project Details
State
NV
County
Clark
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Mohave Substation 500kV
Data Source
LBNL + Live
No news available for this project.