REXFORD 2 SOLAR FARM
BetaActiveSolarBatteryCAISOLBNL + Live
400 MW hybrid in Tulare, CA · In queue since April 2020 · Proposed COD July 2027
400 MW
Capacity
2
Components
Solar + Battery
5y 11m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 3m
Impact Study25%
Queue EntryApr 15, 2020
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-01
Technology
Solar200 MW · 50%
Battery200 MW · 50%
Project Details
State
CA
County
Tulare
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Vestal Substation 230kV
Data Source
LBNL + Live
No news available for this project.