BELLEFIELD 3 SOLAR FARM
BetaActiveSolarBatteryCAISOLBNL + Live
300 MW hybrid in Kern, CA · In queue since April 2020 · Proposed COD April 2027
300 MW
Capacity
2
Components
Solar + Battery
5y 11m
In Queue
IA Executed
IA Status
Signed Jun 2023
Interconnection Timeline
Queue → IA
3y 2m
IA → COD
3y 10m
Total Duration
3y 2m
Construction75%
Queue EntryApr 15, 2020
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementJun 28, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2027-04-01
Technology
Solar150 MW · 50%
Battery150 MW · 50%
Project Details
State
CA
County
Kern
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Windhub Substation 230kV
Data Source
LBNL + Live
No news available for this project.