SEGS EXPANSION 2 HYBRID — Project Summary

Queue ID
CAISO-1775
Capacity
145 MW
Technology
Solar+Battery
Status
active
Location
San Bernardino, CA
Region
CAISO
Developer
IA Status
IA Executed

SEGS EXPANSION 2 HYBRID

BetaActiveSolarBatteryCAISOLBNL + Live

145 MW hybrid in San Bernardino, CA · In queue since April 2020 · Proposed COD November 2026

145 MW

Capacity

2

Components

Solar + Battery

5y 11m

In Queue

IA Executed

IA Status

Signed Oct 2023

Interconnection Timeline

Queue → IA

3y 6m

IA → COD

3y 1m

Total Duration

3y 6m

Construction75%
Queue EntryApr 15, 2020

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementOct 31, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-11-02

Technology
Solar100 MW · 69%
Battery45 MW · 31%
Project Details

State

CA

County

San Bernardino

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

Kramer Junction Substation 230kV

Data Source

LBNL + Live

No news available for this project.