SAPPHIRE SOLAR
243.291 MW hybrid in Riverside, CA · In queue since April 2020 · Proposed COD December 2034
243.291 MW
Capacity
2
Components
Solar + Battery
5y 11m
In Queue
IA Executed
IA Status
COD target: 2034
Total Duration
14y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2034-12-31
State
CA
County
Riverside
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Red Bluff Substation 230kV
Data Source
LBNL + Live
Solar-storage PPA between EDF, Southern California Public Power Authority scrapped over rising costs
A power purchase agreement (PPA) between EDF Renewables North America and Southern California Public Power Authority (SCPPA) has been terminated.
Solar-storage PPA between EDF, Southern California Public Power Authority scrapped over rising costs
A power purchase agreement (PPA) between EDF Renewables North America and Southern California Public Power Authority (SCPPA) has been terminated.
Solar-storage PPA between EDF, Southern California Public Power Authority scrapped over rising costs
A power purchase agreement (PPA) between EDF Renewables North America and Southern California Public Power Authority (SCPPA) has been terminated.
Solar-storage PPA between EDF, Southern California Public Power Authority scrapped over rising costs
A power purchase agreement (PPA) between EDF Renewables North America and Southern California Public Power Authority (SCPPA) has been terminated.
Last updated 2026-03-26