WINDWALKER OFFSHORE
BetaActiveOffshore WindCAISOLBNL + Live
1,028.94 MW generation in San Luis Obispo, CA · In queue since April 2020 · Proposed COD February 2028
1,028.94 MW
Capacity
1
Components
Offshore Wind
5y 11m
In Queue
IA Executed
IA Status
Signed Jan 2023
Interconnection Timeline
Queue → IA
2y 9m
IA → COD
5y 1m
Total Duration
2y 9m
Construction75%
Queue EntryApr 15, 2020
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementJan 8, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 36–60 months
Commercial Operation
Proposed COD: 2028-02-12
Project Details
State
CA
County
San Luis Obispo
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Diablo Canyon 500 kV
Data Source
LBNL + Live
No news available for this project.