POTENTIA-VIRIDI — Project Summary

Queue ID
CAISO-1702
Capacity
1224.74 MW
Technology
Solar+Battery
Status
active
Location
San Joaquin, CA
Region
CAISO
Developer
IA Status
IA Executed

POTENTIA-VIRIDI

BetaActiveSolarWindBatteryCAISOLBNL + Live

1,224.74 MW hybrid in San Joaquin, CA · In queue since April 2020 · Proposed COD May 2028

1,224.74 MW

Capacity

3

Components

Solar + Wind + Battery

5y 11m

In Queue

IA Executed

IA Status

Signed Oct 2022

Interconnection Timeline

Queue → IA

2y 6m

IA → COD

5y 7m

Total Duration

2y 6m

Construction75%
Queue EntryApr 15, 2020

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementOct 31, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2028-05-11

Technology
Solar410.04 MW · 33%
Wind408.8 MW · 33%
Battery405.9 MW · 33%
Project Details

State

CA

County

San Joaquin

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Tesla 500 kV

Data Source

LBNL + Live