DENALI ENERGY STORAGE — Project Summary

Queue ID
CAISO-1690
Capacity
102 MW
Technology
Battery
Status
active
Location
San Joaquin, CA
Region
CAISO
Developer
IA Status
IA Executed

DENALI ENERGY STORAGE

BetaActiveBatteryCAISOLBNL + Live

102 MW storage in San Joaquin, CA · In queue since April 2020 · Proposed COD September 2028

102 MW

Capacity

1

Components

Battery

5y 11m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

8y 5m

Construction75%
Queue EntryApr 15, 2020

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2028-09-30

Project Details

State

CA

County

San Joaquin

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Vierra 115 kV

Data Source

LBNL + Live