CONAWAY HYBRID POWER PLANT
BetaActiveSolarBatteryCAISOLBNL + Live
169.807 MW hybrid in Yolo, CA · In queue since April 2020 · Proposed COD January 2023
169.807 MW
Capacity
2
Components
Solar + Battery
5y 11m
In Queue
System Impact Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 9m
Schedule
39 months past proposed COD
Impact Study25%
Queue EntryApr 15, 2020
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-01-01
Technology
Solar84.996 MW · 50%
Battery84.812 MW · 50%
Project Details
State
CA
County
Yolo
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Woodland-Davis 115 kV Line
Data Source
LBNL + Live
No news available for this project.