NIGHTHAWK STORAGE
BetaActiveBatteryCAISOLBNL + Live
300 MW storage in San Diego, CA · In queue since April 2019 · Proposed COD March 2026
300 MW
Capacity
1
Components
Battery
6y 11m
In Queue
IA Executed
IA Status
Signed Jul 2021
Interconnection Timeline
Queue → IA
2y 3m
IA → COD
4y 8m
Total Duration
2y 3m
Schedule
1 months past proposed COD
Construction75%
Queue EntryApr 15, 2019
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementJul 15, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-03-01
Project Details
State
CA
County
San Diego
Region
CAISO
Developer
—
Utility
SDGE
Entity
CAISO
Point of Interconnection
Sycamore Canyon Substation 138 kV