SUNRISE BUTTE
BetaActiveSolarBatteryCAISOLBNL + Live
150 MW hybrid in Imperial, CA · In queue since April 2019 · Proposed COD November 2029
150 MW
Capacity
1
Components
Battery
6y 11m
In Queue
IA Executed
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
10y 7m
Construction75%
Queue EntryApr 15, 2019
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2029-11-18
Project Details
State
CA
County
Imperial
Region
CAISO
Developer
—
Utility
SDGE
Entity
CAISO
Point of Interconnection
Imperial Valley Substation 230 kV
Data Source
LBNL + Live