HOODINI — Project Summary

Queue ID
CAISO-1663
Capacity
572.17 MW
Technology
Solar+Battery
Status
active
Location
Yuma, AZ
Region
CAISO
Developer
IA Status
System Impact Study

HOODINI

BetaActiveSolarBatteryCAISOLBNL + Live

572.17 MW hybrid in Yuma, AZ · In queue since April 2019 · Proposed COD January 2028

572.17 MW

Capacity

2

Components

Solar + Battery

6y 11m

In Queue

System Impact Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

8y 9m

Impact Study25%
Queue EntryApr 15, 2019

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-01-31

Technology
Solar459.54 MW · 80%
Battery112.63 MW · 20%
Project Details

State

AZ

County

Yuma

Region

CAISO

Developer

Utility

SDGE

Entity

CAISO

Point of Interconnection

Hoodoo Wash Switchyard 500 kV

Data Source

LBNL + Live