CIMARRON WIND — Project Summary

Queue ID
CAISO-1660
Capacity
352.5 MW
Technology
Wind
Status
active
Location
Tecate, MX
Region
CAISO
Developer
IA Status
IA Executed

CIMARRON WIND

BetaActiveWindCAISOLBNL + Live

352.5 MW generation in Tecate, MX · In queue since April 2019 · Proposed COD December 2025

352.5 MW

Capacity

1

Components

Wind

6y 11m

In Queue

IA Executed

IA Status

Signed Dec 2023

Interconnection Timeline

Queue → IA

4y 8m

IA → COD

2 years

Total Duration

4y 8m

Schedule

3 months past proposed COD

Construction75%
Queue EntryApr 15, 2019

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementDec 21, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

MX

County

Tecate

Region

CAISO

Developer

Utility

SDGE

Entity

CAISO

Point of Interconnection

East County Substation 230 kV

Data Source

LBNL + Live

No news available for this project.