CIMARRON WIND
BetaActiveWindCAISOLBNL + Live
352.5 MW generation in Tecate, MX · In queue since April 2019 · Proposed COD December 2025
352.5 MW
Capacity
1
Components
Wind
6y 11m
In Queue
IA Executed
IA Status
Signed Dec 2023
Interconnection Timeline
Queue → IA
4y 8m
IA → COD
2 years
Total Duration
4y 8m
Schedule
3 months past proposed COD
Construction75%
Queue EntryApr 15, 2019
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementDec 21, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
MX
County
Tecate
Region
CAISO
Developer
—
Utility
SDGE
Entity
CAISO
Point of Interconnection
East County Substation 230 kV
Data Source
LBNL + Live
No news available for this project.