BONANZA PEAK SOLAR FARM — Project Summary

Queue ID
CAISO-1655
Capacity
641 MW
Technology
Solar+Battery
Status
active
Location
Clark, NV
Region
CAISO
Developer
IA Status
IA Executed

BONANZA PEAK SOLAR FARM

BetaActiveSolarBatteryCAISOLBNL + Live

641 MW hybrid in Clark, NV · In queue since April 2019 · Proposed COD December 2027

641 MW

Capacity

2

Components

Solar + Battery

6y 11m

In Queue

IA Executed

IA Status

Signed Jun 2022

Interconnection Timeline

Queue → IA

3y 2m

IA → COD

5y 6m

Total Duration

3y 2m

Construction75%
Queue EntryApr 12, 2019

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementJun 8, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2027-12-31

Technology
Solar441 MW · 69%
Battery200 MW · 31%
Project Details

State

NV

County

Clark

Region

CAISO

Developer

Utility

GLW

Entity

CAISO

Point of Interconnection

Trout Canyon Substation 230 kV

Data Source

LBNL + Live