BONANZA PEAK SOLAR FARM
BetaActiveSolarBatteryCAISOLBNL + Live
641 MW hybrid in Clark, NV · In queue since April 2019 · Proposed COD December 2027
641 MW
Capacity
2
Components
Solar + Battery
6y 11m
In Queue
IA Executed
IA Status
Signed Jun 2022
Interconnection Timeline
Queue → IA
3y 2m
IA → COD
5y 6m
Total Duration
3y 2m
Construction75%
Queue EntryApr 12, 2019
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementJun 8, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2027-12-31
Technology
Solar441 MW · 69%
Battery200 MW · 31%
Project Details
State
NV
County
Clark
Region
CAISO
Developer
—
Utility
GLW
Entity
CAISO
Point of Interconnection
Trout Canyon Substation 230 kV
Data Source
LBNL + Live
No news available for this project.