YELLOW PINE 3 — Project Summary

Queue ID
CAISO-1654
Capacity
516.934 MW
Technology
Solar+Battery
Status
active
Location
Clark, NV
Region
CAISO
Developer
IA Status
IA Executed

YELLOW PINE 3

BetaActiveSolarBatteryCAISOLBNL + Live

516.934 MW hybrid in Clark, NV · In queue since April 2019 · Proposed COD December 2026

516.934 MW

Capacity

2

Components

Solar + Battery

6y 11m

In Queue

IA Executed

IA Status

Signed Mar 2023

Interconnection Timeline

Queue → IA

3y 11m

IA → COD

3y 9m

Total Duration

3y 11m

Construction75%
Queue EntryApr 15, 2019

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementMar 1, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-12-01

Technology
Solar261.954 MW · 51%
Battery254.98 MW · 49%
Project Details

State

NV

County

Clark

Region

CAISO

Developer

Utility

GLW

Entity

CAISO

Point of Interconnection

Trout Canyon Substation 230 kV

Data Source

LBNL + Live