ROUGH HAT HYBRID SOLAR
BetaActiveSolarBatteryCAISOLBNL + Live
404 MW hybrid in Nye, NV · In queue since April 2019 · Proposed COD July 2028
404 MW
Capacity
2
Components
Solar + Battery
6y 11m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
9y 3m
Construction75%
Queue EntryApr 15, 2019
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2028-07-31
Technology
Solar204 MW · 50%
Battery200 MW · 50%
Project Details
State
NV
County
Nye
Region
CAISO
Developer
—
Utility
GLW
Entity
CAISO
Point of Interconnection
Trout Canyon Substation 230 kV
Data Source
LBNL + Live