ARIDA 2 SOLAR FARM
BetaActiveSolarBatteryCAISOLBNL + Live
1,400 MW hybrid in Clark, NV · In queue since April 2019 · Proposed COD May 2029
1,400 MW
Capacity
2
Components
Solar + Battery
6y 11m
In Queue
System Impact Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
10y 1m
Impact Study25%
Queue EntryApr 15, 2019
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-05-31
Technology
Solar700 MW · 50%
Battery700 MW · 50%
Project Details
State
NV
County
Clark
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Mohave Substation 500kV
Data Source
LBNL + Live
No news available for this project.