ARIDA 2 SOLAR FARM — Project Summary

Queue ID
CAISO-1647
Capacity
1400 MW
Technology
Solar+Battery
Status
active
Location
Clark, NV
Region
CAISO
Developer
IA Status
System Impact Study

ARIDA 2 SOLAR FARM

BetaActiveSolarBatteryCAISOLBNL + Live

1,400 MW hybrid in Clark, NV · In queue since April 2019 · Proposed COD May 2029

1,400 MW

Capacity

2

Components

Solar + Battery

6y 11m

In Queue

System Impact Study

IA Status

COD target: 2029

Interconnection Timeline

Total Duration

10y 1m

Impact Study25%
Queue EntryApr 15, 2019

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-05-31

Technology
Solar700 MW · 50%
Battery700 MW · 50%
Project Details

State

NV

County

Clark

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

Mohave Substation 500kV

Data Source

LBNL + Live

No news available for this project.