LYCAN SOLAR
800 MW hybrid in Riverside, CA · In queue since April 2019 · Proposed COD April 2030
800 MW
Capacity
2
Components
Solar + Battery
6y 11m
In Queue
IA Executed
IA Status
Signed Apr 2023
Queue → IA
4 years
IA → COD
7 years
Total Duration
4 years
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2030-04-01
State
CA
County
Riverside
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Red Bluff Substation 500kV
Data Source
LBNL + Live
Spud Valley solar project on track to build in Alamosa County
Photo of NextEra's 250 MW Thunder Wolf Energy Center project in Pueblo, which is similar to the 200 MW proposed Spud Valley Energy Center...
Spud Valley solar project on track to build in Alamosa County
Photo of NextEra's 250 MW Thunder Wolf Energy Center project in Pueblo, which is similar to the 200 MW proposed Spud Valley Energy Center...
Blackstone invests $1.2bn to develop Wolf Summit Energy project
Blackstone, via funds affiliated with Blackstone Energy Transition Partners, has unveiled a $1.2bn commitment to develop the fully...
Blackstone invests $1.2bn to develop Wolf Summit Energy project
Blackstone, via funds affiliated with Blackstone Energy Transition Partners, has unveiled a $1.2bn commitment to develop the fully...
Last updated 2026-03-26