OBERON
1,036.8 MW hybrid in Riverside, CA · In queue since April 2019 · Proposed COD April 2026
1,036.8 MW
Capacity
2
Components
Solar + Battery
6y 11m
In Queue
IA Executed
IA Status
Signed Apr 2021
Queue → IA
2 years
IA → COD
5 years
Total Duration
2 years
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2026-04-15
State
CA
County
Riverside
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Red Bluff Substation 500kV
Data Source
LBNL + Live
2 Huge Solar-plus-storage Projects Planned in California
Intersect Power is seeking approval for two 1.15-GW solar-plus-storage projects in California using a streamlined permitting process.
2 Huge Solar-plus-storage Projects Planned in California
Intersect Power is seeking approval for two 1.15-GW solar-plus-storage projects in California using a streamlined permitting process.
2 Huge Solar-plus-storage Projects Planned in California
Intersect Power is seeking approval for two 1.15-GW solar-plus-storage projects in California using a streamlined permitting process.
2 Huge Solar-plus-storage Projects Planned in California
Intersect Power is seeking approval for two 1.15-GW solar-plus-storage projects in California using a streamlined permitting process.
Last updated 2026-03-26