SANBORN HYBRID 3 — Project Summary

Queue ID
CAISO-1632
Capacity
1450.0956 MW
Technology
Solar+Battery
Status
active
Location
Kern, CA
Region
CAISO
Developer
IA Status
IA Executed

SANBORN HYBRID 3

BetaActiveSolarBatteryCAISOLBNL + Live

1,450.096 MW hybrid in Kern, CA · In queue since April 2019 · Proposed COD December 2026

1,450.096 MW

Capacity

2

Components

Solar + Battery

6y 11m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

7y 8m

Construction75%
Queue EntryApr 15, 2019

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-12-31

Technology
Solar778.546 MW · 54%
Battery671.55 MW · 46%
Project Details

State

CA

County

Kern

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

Windhub Substation 500kV

Data Source

LBNL + Live