LOCKHART SOLAR 2
164.7 MW hybrid in San Bernardino, CA · In queue since April 2019 · Proposed COD April 2026
164.7 MW
Capacity
2
Components
Solar + Battery
6y 11m
In Queue
IA Executed
IA Status
Signed Oct 2023
Queue → IA
4y 6m
IA → COD
2y 6m
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2026-04-01
State
CA
County
San Bernardino
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Kramer Substation 230kV
Data Source
LBNL + Live
Terra-Gen energises 129-MW battery complex in California
Renewable power producer Terra-Gen has achieved commercial operations at its 128.7-MW/515-MWh Lockhart CL I and II battery storage project...
Ormat Technologies, Terra-Gen commission 655 MWh of battery storage in California - Energy Storage
Two battery energy storage projects with a total capacity of around 655 MWh have begun commercial operations in California.
Terra-Gen energises 129-MW battery complex in California
Renewable power producer Terra-Gen has achieved commercial operations at its 128.7-MW/515-MWh Lockhart CL I and II battery storage project...
Terra-Gen energises 129-MW battery complex in California
Renewable power producer Terra-Gen has achieved commercial operations at its 128.7-MW/515-MWh Lockhart CL I and II battery storage project...
Last updated 2026-03-26