COMMERCE ENERGY STORAGE
BetaActiveBatteryCAISOLBNL + Live
250 MW storage in Los Angeles, CA · In queue since April 2019 · Proposed COD June 2026
250 MW
Capacity
1
Components
Battery
6y 11m
In Queue
IA Executed
IA Status
Signed Jan 2022
Interconnection Timeline
Queue → IA
2y 9m
IA → COD
4y 5m
Total Duration
2y 9m
Construction75%
Queue EntryApr 15, 2019
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementJan 12, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-06-01
Project Details
State
CA
County
Los Angeles
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Laguna Bell Substation 230kV
Data Source
LBNL + Live
No news available for this project.