AVOCET STORAGE
200 MW storage in Los Angeles, CA · In queue since April 2019 · Proposed COD April 2026
200 MW
Capacity
1
Components
Battery
6y 11m
In Queue
IA Executed
IA Status
Signed Jun 2021
Queue → IA
2y 2m
IA → COD
4y 10m
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-04-15
State
CA
County
Los Angeles
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Hinson Substation 230kV
Data Source
LBNL + Live
One of the US’s first solar peaker plants – with Tesla Megapacks – just came online
The $529 million project in Imperial County, California, near Holtville, features 157 megawatts of solar power paired with 150 megawatts/600 megawatt hours of...
One of the US’s first solar peaker plants – with Tesla Megapacks – just came online
The $529 million project in Imperial County, California, near Holtville, features 157 megawatts of solar power paired with 150 megawatts/600 megawatt hours of...
California city green lights Arevon's 800MWh BESS, finds ‘less than significant’ impact on surroundings
IPP Arevon has been given the green light for the construction and operation of a standalone 200MW/800MWh battery energy storage system (BESS) facility in Los...
California city green lights Arevon's 800MWh BESS, finds ‘less than significant’ impact on surroundings
IPP Arevon has been given the green light for the construction and operation of a standalone 200MW/800MWh battery energy storage system (BESS) facility in Los...
Last updated 2026-03-26