BUTTONBUSH SOLAR HYBRID ENERGY CENTER — Project Summary

Queue ID
CAISO-1596
Capacity
1636 MW
Technology
Solar+Battery
Status
active
Location
Kern, CA
Region
CAISO
Developer
IA Status
IA Executed

BUTTONBUSH SOLAR HYBRID ENERGY CENTER

BetaActiveSolarBatteryCAISOLBNL + Live

1,636 MW hybrid in Kern, CA · In queue since April 2019 · Proposed COD December 2026

1,636 MW

Capacity

2

Components

Solar + Battery

6y 11m

In Queue

IA Executed

IA Status

Signed Nov 2021

Interconnection Timeline

Queue → IA

2y 7m

IA → COD

5y 1m

Total Duration

2y 7m

Construction75%
Queue EntryApr 15, 2019

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementNov 15, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-12-01

Technology
Solar818 MW · 50%
Battery818 MW · 50%
Project Details

State

CA

County

Kern

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Midway 500 kV

Data Source

LBNL + Live