PELICANS JAW HYBRID SOLAR — Project Summary

Queue ID
CAISO-1593
Capacity
1000 MW
Technology
Solar+Battery
Status
active
Location
Kings, CA
Region
CAISO
Developer
IA Status
IA Executed

PELICANS JAW HYBRID SOLAR

BetaActiveSolarBatteryCAISOLBNL + Live

1,000 MW hybrid in Kings, CA · In queue since April 2019 · Proposed COD January 2028

1,000 MW

Capacity

2

Components

Solar + Battery

6y 11m

In Queue

IA Executed

IA Status

Signed Sep 2022

Interconnection Timeline

Queue → IA

3y 5m

IA → COD

5y 4m

Total Duration

3y 5m

Construction75%
Queue EntryApr 15, 2019

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementSep 25, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2028-01-24

Technology
Solar500 MW · 50%
Battery500 MW · 50%
Project Details

State

CA

County

Kings

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Gates-Midway 230 kV Line

Data Source

LBNL + Live

No news available for this project.