PELICANS JAW HYBRID SOLAR
BetaActiveSolarBatteryCAISOLBNL + Live
1,000 MW hybrid in Kings, CA · In queue since April 2019 · Proposed COD January 2028
1,000 MW
Capacity
2
Components
Solar + Battery
6y 11m
In Queue
IA Executed
IA Status
Signed Sep 2022
Interconnection Timeline
Queue → IA
3y 5m
IA → COD
5y 4m
Total Duration
3y 5m
Construction75%
Queue EntryApr 15, 2019
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementSep 25, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2028-01-24
Technology
Solar500 MW · 50%
Battery500 MW · 50%
Project Details
State
CA
County
Kings
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Gates-Midway 230 kV Line
Data Source
LBNL + Live
No news available for this project.