KINGSROAD HYBRID SOLAR
BetaActiveSolarBatteryCAISOLBNL + Live
203.56 MW hybrid in Kern, CA · In queue since April 2019 · Proposed COD December 2028
203.56 MW
Capacity
2
Components
Solar + Battery
6y 11m
In Queue
IA Executed
IA Status
Signed Feb 2023
Interconnection Timeline
Queue → IA
3y 10m
IA → COD
5y 10m
Total Duration
3y 10m
Construction75%
Queue EntryApr 15, 2019
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementFeb 14, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2028-12-01
Technology
Solar101.78 MW · 50%
Battery101.78 MW · 50%
Project Details
State
CA
County
Kern
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Arco 230 kV
Data Source
LBNL + Live
No news available for this project.