AIR STATION 1
BetaActiveSolarBatteryCAISOLBNL + Live
42.1 MW hybrid in Kings, CA · In queue since April 2019 · Proposed COD December 2021
42.1 MW
Capacity
2
Components
Solar + Battery
6y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
2y 8m
Schedule
52 months past proposed COD
In Study38%
Queue EntryApr 15, 2019
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-12-31
Technology
Solar21.05 MW · 50%
Battery21.05 MW · 50%
Project Details
State
CA
County
Kings
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Henrietta-Lemoore NAS 70 kV
Data Source
LBNL + Live
No news available for this project.