DYNAMO SOLAR
24.5 MW generation in Napa, CA · In queue since April 2019 · Proposed COD July 2027
24.5 MW
Capacity
1
Components
Solar
6y 11m
In Queue
IA Executed
IA Status
Signed Sep 2021
Queue → IA
2y 5m
IA → COD
5y 10m
Total Duration
2y 5m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-07-16
State
CA
County
Napa
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Tulucay 60 kV
Data Source
LBNL + Live
AIP Management to acquire stake in US solar and energy storage project
AIP Management is set to acquire a stake in Pine Forest, a co-located 300 MWac solar photovoltaics and 200 MW battery energy storage system...
$2 billion in solar panels… but it’s not enough: This state has America on edge
Southern California entered a new era of clean energy in December 2024 with the commissioning of the Eland 1 Solar-plus-Storage Project.
$2 billion in solar panels… but it’s not enough: This state has America on edge
Southern California entered a new era of clean energy in December 2024 with the commissioning of the Eland 1 Solar-plus-Storage Project.
$2 billion in solar panels… but it’s not enough: This state has America on edge
Southern California entered a new era of clean energy in December 2024 with the commissioning of the Eland 1 Solar-plus-Storage Project.
Last updated 2026-03-26