IRVING STORAGE
782.79 MW storage in Monterey, CA · In queue since May 2019 · Proposed COD November 2025
782.79 MW
Capacity
1
Components
Battery
6y 10m
In Queue
IA Executed
IA Status
Signed Jul 2021
Queue → IA
2y 2m
IA → COD
4y 4m
Total Duration
2y 2m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-11-30
State
CA
County
Monterey
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Moss Landing 500 kV
Data Source
LBNL + Live
Residents Oppose New Battery Storage Facilities
Members of the community continued to push back against the introduction of Battery Energy Storage Systems at a July 30 workshop.
Proposed Battery Storage Site in South Orange County Sparks Wildfire Concerns
South Orange County residents and elected officials representing the region are raising wildfire concerns about a proposed battery storage...
Vistra withdraws battery storage application, to seek state approval
Vistra, a Texas-based energy company, has plans to construct and operate a 600-megawatt battery storage facility on approximately 24 acres of a roughly 70-acre...
Vistra withdraws battery storage application, to seek state approval
Vistra, a Texas-based energy company, has plans to construct and operate a 600-megawatt battery storage facility on approximately 24 acres of a roughly 70-acre...
Last updated 2026-03-26