ARIDA SOLAR FARM
BetaActiveSolarBatteryCAISOLBNL + Live
740 MW hybrid in Clark, NV · In queue since April 2018 · Proposed COD September 2027
740 MW
Capacity
2
Components
Solar + Battery
7y 11m
In Queue
System Impact Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
9y 5m
Impact Study25%
Queue EntryApr 16, 2018
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)Current
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-15
Technology
Solar370 MW · 50%
Battery370 MW · 50%
Project Details
State
NV
County
Clark
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Mohave Substation 500kV
Data Source
LBNL + Live
No news available for this project.