BALDY MESA 2 — Project Summary

Queue ID
CAISO-1519
Capacity
125 MW
Technology
Solar+Battery
Status
active
Location
San Bernardino, CA
Region
CAISO
Developer
IA Status
IA Executed

BALDY MESA 2

BetaActiveSolarBatteryCAISOLBNL + Live

125 MW hybrid in San Bernardino, CA · In queue since April 2018 · Proposed COD November 2026

125 MW

Capacity

2

Components

Solar + Battery

7y 11m

In Queue

IA Executed

IA Status

Signed Nov 2020

Interconnection Timeline

Queue → IA

2y 7m

IA → COD

6 years

Total Duration

2y 7m

Construction75%
Queue EntryApr 16, 2018

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementNov 4, 2020

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-11-01

Technology
Solar50 MW · 40%
Battery75 MW · 60%
Project Details

State

CA

County

San Bernardino

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

Roadway Substation 115kV

Data Source

LBNL + Live