BELLEFIELD SOLAR FARM
BetaActiveSolarBatteryCAISOLBNL + Live
1,000 MW hybrid in Kern, CA · In queue since April 2018 · Proposed COD August 2025
1,000 MW
Capacity
2
Components
Solar + Battery
7y 11m
In Queue
IA Executed
IA Status
Signed May 2020
Interconnection Timeline
Queue → IA
2y 1m
IA → COD
5y 3m
Total Duration
2y 1m
Schedule
8 months past proposed COD
Construction75%
Queue EntryApr 16, 2018
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementMay 7, 2020
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2025-08-01
Technology
Solar500 MW · 50%
Battery500 MW · 50%
Project Details
State
CA
County
Kern
Region
CAISO
Developer
—
Utility
SCE
Entity
CAISO
Point of Interconnection
Windhub Substation 230kV
Data Source
LBNL + Live
No news available for this project.