JASMINE
BetaActiveSolarBatteryCAISOLBNL + Live
141.161 MW hybrid in Kern, CA · In queue since April 2018 · Proposed COD August 2026
141.161 MW
Capacity
2
Components
Solar + Battery
7y 11m
In Queue
IA Executed
IA Status
Signed Jun 2020
Interconnection Timeline
Queue → IA
2y 2m
IA → COD
6y 2m
Total Duration
2y 2m
Construction75%
Queue EntryApr 16, 2018
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementJun 5, 2020
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2026-08-31
Technology
Solar71.161 MW · 50%
Battery70 MW · 50%
Project Details
State
CA
County
Kern
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Lakeview 70 kV
Data Source
LBNL + Live
News & Articles (1)Beta