CHALAN SOLAR
91.8 MW hybrid in Kern, CA · In queue since April 2018 · Proposed COD April 2026
91.8 MW
Capacity
2
Components
Solar + Battery
7y 11m
In Queue
IA Executed
IA Status
Signed Dec 2021
Queue → IA
3y 8m
IA → COD
4y 4m
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2026-04-12
State
CA
County
Kern
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Arco 230 kV
Data Source
LBNL + Live
Origis Energy and Pioneer Community Energy Announce 20-Year Solar + Battery Storage Agreement
Rocklin, CA – Origis Energy, one of America's leading renewable energy and decarbonization solution platforms, and Pioneer Community Energy...
Origis Energy and Pioneer Community Energy Announce 20-Year Solar + Battery Storage Agreement
Rocklin, CA – Origis Energy, one of America's leading renewable energy and decarbonization solution platforms, and Pioneer Community Energy...
Origis Energy and Pioneer Community Energy Announce 20-Year Solar + Battery Storage Agreement
Rocklin, CA – Origis Energy, one of America's leading renewable energy and decarbonization solution platforms, and Pioneer Community Energy...
Last updated 2026-03-26