AZALEA — Project Summary

Queue ID
CAISO-1493
Capacity
99.3 MW
Technology
Solar+Battery
Status
active
Location
Kern, CA
Region
CAISO
Developer
IA Status
IA Executed

AZALEA

BetaActiveSolarBatteryCAISOLBNL + Live

99.3 MW hybrid in Kern, CA · In queue since April 2018 · Proposed COD September 2025

99.3 MW

Capacity

2

Components

Solar + Battery

7y 11m

In Queue

IA Executed

IA Status

Signed Jun 2020

Interconnection Timeline

Queue → IA

2y 2m

IA → COD

5y 3m

Total Duration

2y 2m

Schedule

7 months past proposed COD

Construction75%
Queue EntryApr 16, 2018

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementJun 11, 2020

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2025-09-12

Technology
Solar61.3 MW · 62%
Battery38 MW · 38%
Project Details

State

CA

County

Kern

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Arco 70 kV