KEY STORAGE 1 — Project Summary

Queue ID
CAISO-1479
Capacity
309.3 MW
Technology
Battery
Status
active
Location
Fresno, CA
Region
CAISO
Developer
IA Status
IA Executed

KEY STORAGE 1

BetaActiveBatteryCAISOLBNL + Live

309.3 MW storage in Fresno, CA · In queue since April 2018 · Proposed COD October 2026

309.3 MW

Capacity

1

Components

Battery

7y 11m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

8y 6m

Construction75%
Queue EntryApr 16, 2018

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-10-01

Project Details

State

CA

County

Fresno

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Gates 500 kV

Data Source

LBNL + Live