SOLANO 4 WIND
92.354 MW generation in Solano, CA · In queue since April 2018 · Proposed COD May 2025
92.354 MW
Capacity
1
Components
Wind
7y 11m
In Queue
IA Executed
IA Status
Signed Feb 2023
Queue → IA
4y 10m
IA → COD
2y 3m
Total Duration
4y 10m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2025-05-31
State
CA
County
Solano
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Birds Landing 230 kV
Data Source
LBNL + Live
Environmental groups rally against proposed carbon dioxide pipeline in Solano County
The Montezuma NorCal Carbon Sequestration Hub is currently waiting on a permit from Solano County to build a test well.
In quest to get to zero-carbon power by 2030, SMUD has some work to do
The Sacramento Municipal Utility District is halfway through its timeline of getting to zero emissions by 2030, and it's getting closer to the goal.
In quest to get to zero-carbon power by 2030, SMUD has some work to do
The Sacramento Municipal Utility District is halfway through its timeline of getting to zero emissions by 2030, and it's getting closer to the goal.
In quest to get to zero-carbon power by 2030, SMUD has some work to do
The Sacramento Municipal Utility District is halfway through its timeline of getting to zero emissions by 2030, and it's getting closer to the goal.
Last updated 2026-03-26