RECLAIMED WIND — Project Summary

Queue ID
CAISO-1461
Capacity
114.4 MW
Technology
Battery
Status
active
Location
Alameda, CA
Region
CAISO
Developer
IA Status
IA Executed

RECLAIMED WIND

BetaActiveBatteryCAISOLBNL + Live

114.4 MW storage in Alameda, CA · In queue since April 2018 · Proposed COD December 2026

114.4 MW

Capacity

1

Components

Battery

7y 11m

In Queue

IA Executed

IA Status

Signed Mar 2022

Interconnection Timeline

Queue → IA

3y 11m

IA → COD

4y 9m

Total Duration

3y 11m

Construction75%
Queue EntryApr 16, 2018

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementMar 12, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-12-01

Project Details

State

CA

County

Alameda

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Kelso-Tesla Tap 230 kV

Data Source

LBNL + Live