MULQUEENEY RANCH WIND 2
BetaActiveWindCAISOLBNL + Live
62.5 MW generation in Alameda, CA · In queue since April 2018 · Proposed COD June 2026
62.5 MW
Capacity
1
Components
Wind
7y 11m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
8y 2m
Construction75%
Queue EntryApr 16, 2018
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-06-01
Project Details
State
CA
County
Alameda
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Tesla 230 kV
Data Source
LBNL + Live
No news available for this project.