MILPA POWER BANK — Project Summary

Queue ID
CAISO-1457
Capacity
3 MW
Technology
Battery
Status
active
Location
Santa Clara, CA
Region
CAISO
Developer
IA Status
System Impact Study

MILPA POWER BANK

BetaActiveBatteryCAISOLBNL + Live

3 MW storage in Santa Clara, CA · In queue since April 2018 · Proposed COD April 2025

3 MW

Capacity

1

Components

Battery

7y 11m

In Queue

System Impact Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

7 years

Schedule

11 months past proposed COD

Impact Study25%
Queue EntryApr 16, 2018

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-04-29

Project Details

State

CA

County

Santa Clara

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Los Esteros 115 kV

Data Source

LBNL + Live

No news available for this project.