LAS CAMAS 3
BetaActiveSolarBatteryCAISOLBNL + Live
202.5 MW hybrid in Merced, CA · In queue since April 2018 · Proposed COD December 2027
202.5 MW
Capacity
2
Components
Solar + Battery
7y 11m
In Queue
IA Executed
IA Status
Signed Mar 2022
Interconnection Timeline
Queue → IA
3y 11m
IA → COD
5y 9m
Total Duration
3y 11m
Construction75%
Queue EntryApr 16, 2018
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementMar 28, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2027-12-31
Technology
Solar102.5 MW · 51%
Battery100 MW · 49%
Project Details
State
CA
County
Merced
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Los Banos 230 kV
Data Source
LBNL + Live
No news available for this project.