JANUS
BetaActiveSolarBatteryCAISOLBNL + Live
163.54 MW hybrid in Colusa, CA · In queue since April 2018 · Proposed COD March 2027
163.54 MW
Capacity
2
Components
Solar + Battery
7y 11m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
8y 11m
Construction75%
Queue EntryApr 16, 2018
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2027-03-01
Technology
Solar83.54 MW · 51%
Battery80 MW · 49%
Project Details
State
CA
County
Colusa
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Cortina 60 kV
Data Source
LBNL + Live
No news available for this project.