SALOON ENERGY STORAGE
BetaActiveBatteryCAISOLBNL + Live
150 MW storage in Colusa, CA · In queue since April 2018 · Proposed COD July 2027
150 MW
Capacity
1
Components
Battery
7y 11m
In Queue
IA Executed
IA Status
Signed Feb 2024
Interconnection Timeline
Queue → IA
5y 10m
IA → COD
3y 5m
Total Duration
5y 10m
Construction75%
Queue EntryApr 16, 2018
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection AgreementFeb 27, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2027-07-13
Project Details
State
CA
County
Colusa
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Cortina 115 kV
Data Source
LBNL + Live
No news available for this project.