ANGELA — Project Summary

Queue ID
CAISO-1443
Capacity
60 MW
Technology
Solar+Battery
Status
active
Location
Tulare, CA
Region
CAISO
Developer
IA Status
IA Executed

ANGELA

BetaActiveSolarBatteryCAISOLBNL + Live

60 MW hybrid in Tulare, CA · In queue since April 2018 · Proposed COD December 2025

60 MW

Capacity

2

Components

Solar + Battery

7y 11m

In Queue

IA Executed

IA Status

Signed Oct 2020

Interconnection Timeline

Queue → IA

2y 6m

IA → COD

5y 2m

Total Duration

2y 6m

Schedule

3 months past proposed COD

Construction75%
Queue EntryApr 16, 2018

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementOct 30, 2020

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2025-12-15

Technology
Solar40 MW · 67%
Battery20 MW · 33%
Project Details

State

CA

County

Tulare

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Olive 115 kV

Data Source

LBNL + Live