ANGELA
60 MW hybrid in Tulare, CA · In queue since April 2018 · Proposed COD December 2025
60 MW
Capacity
2
Components
Solar + Battery
7y 11m
In Queue
IA Executed
IA Status
Signed Oct 2020
Queue → IA
2y 6m
IA → COD
5y 2m
Total Duration
2y 6m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-12-15
State
CA
County
Tulare
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Olive 115 kV
Data Source
LBNL + Live
Massive increase in nuclear power rates. Welcome to 2026!
By Angela Bischoff, Director Ontario Clean Air Alliance. January 12th, 2026. BURLINGTON, ON. If you thought life was going to get more affordable,...
Statement: Ottawa Council Applauded for Advancing Landmark Battery Storage Project
ENVIRONMENTAL DEFENCE, COMMUNITY ACTION FOR ENVIRONMENTAL SUSTAINABILITY (CAFES) Toronto | Traditional territories of the Mississaugas of...
APA revs up gas power ambitions with $1b commitment
Gas pipeline giant APA Group will join Queensland state-owned CS Energy in a $1 billion-plus gas power plant to be built in the Western...
APA revs up gas power ambitions with $1b commitment
Gas pipeline giant APA Group will join Queensland state-owned CS Energy in a $1 billion-plus gas power plant to be built in the Western...
Last updated 2026-03-26