AJO POWER BANK
BetaActiveBatteryCAISOLBNL + Live
124.3 MW storage in Santa Clara, CA · In queue since April 2018 · Proposed COD January 2028
124.3 MW
Capacity
1
Components
Battery
7y 11m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
9y 9m
Construction75%
Queue EntryApr 16, 2018
Interconnection request submitted to ISO/RTO
Cluster Study (Phase I/II)
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2028-01-01
Project Details
State
CA
County
Santa Clara
Region
CAISO
Developer
—
Utility
PGAE
Entity
CAISO
Point of Interconnection
Llagas-Gilroy Foods 115 kV line
Data Source
LBNL + Live