MOUNT LAGUNA WIND 2
400 MW generation in San Diego, CA · In queue since May 2017 · Proposed COD February 2031
400 MW
Capacity
1
Components
Wind
8y 10m
In Queue
IA Executed
IA Status
Signed Jun 2023
Queue → IA
6y 1m
IA → COD
7y 8m
Total Duration
6y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2031-02-05
State
CA
County
San Diego
Region
CAISO
Developer
—
Utility
SDGE
Entity
CAISO
Point of Interconnection
Suncrest - Ocotillo 500 kV Line
Data Source
LBNL + Live
Spain’s ACCIONA powers up Laguna’s Kalayaan 2 wind farm with first turbine
Spanish renewable energy firm ACCIONA Energía has installed the first turbine at its 101-megawatt (MW) Kalayaan 2 Wind Farm in Laguna,...
Spain’s ACCIONA powers up Laguna’s Kalayaan 2 wind farm with first turbine
Spanish renewable energy firm ACCIONA Energía has installed the first turbine at its 101-megawatt (MW) Kalayaan 2 Wind Farm in Laguna,...
Spain’s ACCIONA powers up Laguna’s Kalayaan 2 wind farm with first turbine
Spanish renewable energy firm ACCIONA Energía has installed the first turbine at its 101-megawatt (MW) Kalayaan 2 Wind Farm in Laguna,...
Spain’s ACCIONA powers up Laguna’s Kalayaan 2 wind farm with first turbine
Spanish renewable energy firm ACCIONA Energía has installed the first turbine at its 101-megawatt (MW) Kalayaan 2 Wind Farm in Laguna,...
Last updated 2026-03-26