CAMINO SOLAR — Project Summary

Queue ID
CAISO-1419
Capacity
58.28 MW
Technology
Solar+Battery
Status
active
Location
Kern, CA
Region
CAISO
Developer
IA Status
IA Executed

CAMINO SOLAR

BetaActiveSolarBatteryCAISOLBNL + Live

58.28 MW hybrid in Kern, CA · In queue since May 2017 · Proposed COD December 2027

58.28 MW

Capacity

2

Components

Solar + Battery

8y 10m

In Queue

IA Executed

IA Status

Signed Nov 2019

Interconnection Timeline

Queue → IA

2y 6m

IA → COD

8y 1m

Total Duration

2y 6m

Construction75%
Queue EntryMay 1, 2017

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementNov 20, 2019

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2027-12-31

Technology
Solar44.88 MW · 77%
Battery13.4 MW · 23%
Project Details

State

CA

County

Kern

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

Whirlwind Substation 230kV

Data Source

LBNL + Live

No news available for this project.