BALDY MESA — Project Summary

Queue ID
CAISO-1413
Capacity
225 MW
Technology
Solar+Battery
Status
active
Location
San Bernardino, CA
Region
CAISO
Developer
IA Status
IA Executed

BALDY MESA

BetaActiveSolarBatteryCAISOLBNL + Live

225 MW hybrid in San Bernardino, CA · In queue since May 2017 · Proposed COD November 2026

225 MW

Capacity

2

Components

Solar + Battery

8y 10m

In Queue

IA Executed

IA Status

Signed Nov 2020

Interconnection Timeline

Queue → IA

3y 6m

IA → COD

6 years

Total Duration

3y 6m

Construction75%
Queue EntryMay 1, 2017

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementNov 9, 2020

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-11-01

Technology
Solar150 MW · 67%
Battery75 MW · 33%
Project Details

State

CA

County

San Bernardino

Region

CAISO

Developer

Utility

SCE

Entity

CAISO

Point of Interconnection

Roadway Substation 115kV bus

Data Source

LBNL + Live