ATLAS COMPLEX
5,120 MW hybrid in La Paz, AZ · In queue since May 2017 · Proposed COD January 2026
5,120 MW
Capacity
2
Components
Solar + Battery
8y 10m
In Queue
IA Executed
IA Status
Signed Jan 2021
Queue → IA
3y 8m
IA → COD
5 years
Total Duration
3y 8m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2026-01-01
State
AZ
County
La Paz
Region
CAISO
Developer
—
Utility
DCRT
Entity
CAISO
Point of Interconnection
Delaney-Colorado River 500 kV Line
Data Source
LBNL + Live
Atlas Renewable Energy closes Latin America's largest clean energy storage refinancing at $3 billion
Atlas Renewable Energy secures $3bn refinancing for solar and battery projects in Chile, boosting clean energy growth in Latin America.
National lab projects enhanced geothermal cost could decline to $100/MWh by 2035
Declining costs for enhanced geothermal could make the technology a stronger competitor to solar plus storage. A national lab atlas shows...
Energy Storage Financing of the Year – Estepa I and II Solar PV + BESS Project
Chile has become the proving ground for large-scale renewable energy storage in Latin America, and Atlas Renewable Energy is at the...
Atlas Renewable Energy secures US$179 million to build 579MW Brazilian solar complex
The project consists of 11 solar PV plant and is the latest partnership between Atlas Renewable Energy and BNDES. Image: Atlas Renewable...
Last updated 2026-03-26