SONRISA — Project Summary

Queue ID
CAISO-1391
Capacity
384 MW
Technology
Solar+Battery
Status
active
Location
Fresno, CA
Region
CAISO
Developer
IA Status
IA Executed

SONRISA

BetaActiveSolarBatteryCAISOLBNL + Live

384 MW hybrid in Fresno, CA · In queue since May 2017 · Proposed COD December 2026

384 MW

Capacity

2

Components

Solar + Battery

8y 10m

In Queue

IA Executed

IA Status

Signed Sep 2020

Interconnection Timeline

Queue → IA

3y 4m

IA → COD

6y 3m

Total Duration

3y 4m

Construction75%
Queue EntryMay 1, 2017

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementSep 2, 2020

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-12-31

Technology
Solar200 MW · 52%
Battery184 MW · 48%
Project Details

State

CA

County

Fresno

Region

CAISO

Developer

Utility

PGAE

Entity

CAISO

Point of Interconnection

Tranquility 230 kV

Data Source

LBNL + Live